HUNTER POWER PROJECT UPDATE

16/12/2024

Testing and commissioning of Snowy Hydro’s fourth fast-start, on demand gas power station has now begun.

This first phase of commissioning involves pressure testing the Hunter Power Project’s (HPP) approximately 23 kilometre network of pipe infrastructure that will deliver gas, diesel and water to the station’s generators. 

Using the latest technology the world’s best manufacturers can offer, HPP will be powered by two of the most gas-efficient turbines available and will be capable of delivering 660 megawatts of electricity to the grid. This significant amount of power will make a meaningful difference to supply reliability, helping the network cope during hot weather and outages of transmission lines and other power stations.

As more wind and solar enters the electricity grid, HPP will play a critical role by providing back-up power to homes and businesses.This means that while HPP is only expected to run around 5 percent of the time, it will enable around 2 gigawatts of renewable energy to be added to the grid, which is the equivalent of displacing around 5 million tonnes of CO2-e every year1.

PHASED COMMISSIONING

Alongside the pipe pressure tests, HPP’s switching station, which was built by Snowy Hydro as part of the project but handed over to Ausgrid to operate, will be connected to provide the power station with energy from the grid. Testing will then progress to commissioning the first of HPP’s two turbines and generators. 

Pending a smooth process, the first turbine and generator is expected to reach full commercial operation by the end of April 2025. Commissioning of the second turbine and generator will follow, with commercial operation of both turbines and generators expected by the end of June 2025. 

Depending on commissioning outcomes, there is a possibility of either turbine being available to provide some power to the grid sooner. These target dates are dependent on the commissioning program not being impacted by weather or other factors.

VALUE AND COST

HPP has experienced extended periods of extreme weather and other factors that have stopped work on the project, impacting its timeline. As flagged in the August 2024 project update, HPP’s cost has been impacted in order to minimise the delay in its completion, so HPP can produce power for the network as soon as possible.

Prioritising power availability means the final cost of HPP is expected to be around $1.3 billion, dependent on a smooth transition to commercial operation without delays from weather or other factors.

Despite the change in cost, the strength of HPP’s economic benefit has increased. HPP’s net present value (NPV), has increased to $914 million from $531 million at the March 2021 final investment decision2

This increase in HPP’s economic value has been largely driven by:

  • more wind and solar generation in the grid increasing the need for HPP to provide on-demand, back-up energy to boost electricity reliability;
  • a substantial increase in HPP’s gas storage capacity to 70TJ from 43TJ;
  • HPP’s contribution to managing transmission risk between Sydney and the Snowy Hydroelectric Scheme in the Snowy Mountains, by providing an alternative electricity source for Australia’s largest economy in the event of transmission outages. 

LOCAL BENEFITS

The project is delivering substantial jobs and investment benefits to the Hunter region:

To promote interest in STEM career paths and education, HPP’s team has engaged with local students through career expos and presentations, including through partnerships with the Clontarf Foundation in Kurri Kurri, Youth Express and Training Services NSW. 

$751 million spent domestically, with $619 million spent in the local Hunter region.  

57% of HPP’s workforce are local residents.  

20 apprentices are engaged on the project, providing skill development in the Hunter region.

Over $175,000 has been awarded to 39 local projects through the HPP Community Grants Program.  

Over $26,000 has been granted to Cessnock LGA schools through the Snowy Hydro Local Schools STEM Fund in 2024.  

1Assumes every 1 MW of dispatchable capacity from HPP enables 3 MW of variable renewable capacity and displaces thermal generation with a carbon intensity of 0.94 t/CO2-e/MWh. Scope 1 emissions from HPP are estimated to be approximately 0.14 million tonnes of CO2-e per annum based on a carbon intensity of 0.52 t/CO2-e/MWh.

 2NPVs discounted to March 2021.

News

HUNTER POWER PROJECT DELIVERS LOCAL JOBS AND SKILLS

12/08/2024

Snowy Hydro’s Hunter Power Project (HPP) is leaving a lasting impact on the local workforce, delivering approximately 600 direct construction jobs and crucial skills development for a number of high-demand construction trades.

More than 60% of HPP workers live locally, which is part of Snowy Hydro’s commitment to supporting communities that the company is a part of.

The number of apprentices at HPP is on the increase, with Snowy Hydro working alongside principal contractor UGL to provide an additional 12 apprenticeship positions in June 2024, which includes three females and two First Nations apprentices. New apprentices on site include a boilermaker, nine electricians, and two mechanical fitters.

Snowy Hydro CEO Dennis Barnes said HPP will be good for jobs long after construction is complete.

“We are proud of our contribution to the construction, engineering, and infrastructure sector here in the Hunter, especially given the current tradespeople shortages in Australia.

“This project will have a lasting impact on the size and proficiency of the local workforce”

Mr Barnes said.

”A job on HPP will help set our team up for a rewarding career and a bright future.”

Electrical apprentice Daniel Battle said he became interested in the electrical trade after working as a Trades Assistant on the project.

“This apprenticeship is giving me the necessary skills, knowledge, and experience while working to a high standard within the industry to become an electrician,” Mr Battle said.

Apprentice boilermaker Jackson Scott said he was passionate about fabrication and welding. “I was very lucky to be offered an apprenticeship shortly after starting at HPP.

“HPP is preparing me to have a successful career contributing to important infrastructure in our country, and I’m extremely grateful,” Mr Scott said.

Electrical apprentice Camilla Lindeberg said she worked as a cleaner for seven months before applying for an apprenticeship.

“I never thought of being an electrical apprentice until the opportunity presented itself, and I’m excited for what the future holds.

“The challenge of learning something new and directly contributing to building HPP gives me a great sense of achievement and sets me up for a whole new career with endless opportunities,” Ms Lindeberg said.

Snowy Hydro is also looking to the future workforce through its community support programme.

In 2024, Snowy Hydro extended its Local School STEM Fund to the Cessnock LGA where HPP is located. More than $26,000 was awarded to schools in the area to foster learning opportunities and career pathways for local young people with a focus on STEM.

From left to right: Daniel Battle, Camilla Lindeberg, and Jackson Scott.
News

SNOWY HYDRO SIGNS LOCHARD GAS STORAGE AGREEMENT

15/07/2024

Snowy Hydro has entered into a 25-year gas storage agreement with Lochard Energy at the Iona underground gas storage facility to support Snowy Hydro’s gas fired generation fleet.

Australia’s energy market continues to experience significant change with the uptake of renewables and the progressive closure of coal fired assets. Snowy Hydro helps manage intermittency in the National Electricity Market (NEM) through its portfolio of power stations including the Snowy Scheme. 

The long-term Lochard storage deal will allow Snowy Hydro to utilise stored gas when required to operate its gas fired power stations.

Snowy Hydro CEO Dennis Barnes said reliability and security of supply is central to the way Snowy Hydro operates, maintains and develops its nationally critical infrastructure. 

“Snowy Hydro’s generating portfolio of hydro, pumping and gas fired power stations continues to support further deployment of renewables into the grid by “firming” intermittent generation sources into reliable power. The gas storage agreement with Lochard Energy will support the operation of our gas-fired power stations in Victoria.”

Lochard CEO Tim Jessen said Lochard welcomes the opportunity to strengthen its relationship with Snowy Hydro through the signing of the new Gas Storage Services Agreement. 

“This important agreement will underpin Lochard’s Heytesbury Underground Gas Storage project through which we will further expand the Iona Gas Storage Facility to continue to provide critical energy storage services in Victoria.”

Gas storage is essential to ensure the supply of gas to meet peak electricity demand in seasonal markets, to supply gas to peak power generators including Snowy Hydro, and to ensure security of supply in the event of supply disruption. 

Snowy Hydro owns and operates three gas-fired power stations, strategically located in the LaTrobe Valley and Laverton in Victoria, and at Colongra, NSW. With a current total generating capacity of 1,290 MW. Snowy Hydro is also constructing a 660MW gas fired power station at Kurri Kurri in the Hunter Valley. 

The Lochard Energy gas storage agreement will commence in January 2028.