News

Tanks construction

04/12/2023

September 2023

Construction of the four tanks at Hunter Power Project are maintaining progress against their target completion dates. A milestone will be reached with the hydro-test of the Service Water Tank, scheduled for the first week in December.

Three of these tanks are constructed with carbon steel: one for service water and the other two for the back-up Diesel fuel. The fourth tank is being constructed of stainless steel and will store demineralised water that is essential for the energy generation process. 

Once finished, these tanks will have a capacity between 2.2 and 2.5 million litres each – approximately the same capacity as an Olympic pool.