Preliminary Alignment Complete

22/04/2024

April 2024

Preliminary alignment of the turbine / generator for both GT1 and GT2 was completed in April 2024. The HPP mechanical team made fine adjustments to the hundredth millimetre, ensuring the generator shaft was perfectly aligned with the turbine shaft. The piping team will step in next, to connect the piping into the turbine and generator casing flanges at their final positions.