IPB to GSUT Completion

24/09/2024

July 2024

At Gas Turbine One (GT1), all three phases of the Isolated Phase Bus (IPB) have been connected from the Generator Step-Up Transformer (GSUT) to the Generator Circuit Breaker (GCB). The HPP team aims to extend the connection from the GCB to GT1 by mid-September 2024. This is an important milestone for HPP with the IPB on the critical path. The IPB carries the power from the Gas Turbine Generator to the GSUT, which is where the power lines start for the transmission.