June 2024
In the civil space at the Hunter Power Project, most services – including trade waste, stormwater systems, oily water systems, fire ring mains, and mechanical services – are completed in the ground. All concrete slabs in GT1, GT2, and Balance of Plant areas are completed except for some minor pipe supports and trenches, infill slabs, and light pole foundations. The civil team will now work on the finishing touches to site with infill pavement slabs, earthworks for pavements, and remaining pits and bollards.