News

SNOWY 2.0 UPDATE

18/07/2024
  • The Snowy Delivery team has completed 570,000 cubic metres of excavation of the Talbingo intake. The intake is where water will exit and enter the tailrace tunnel, connecting the lower Talbingo reservoir to the underground power station
  • Excavation of the Marica surge shaft has reached 95 metres. Mechanical excavation including rock breakers and excavators continues, with drill and blast methods also being used. Once complete, the 28 metre-wide and 250 metre-deep surge shaft will be used for water storage and pressure relief when the power station starts up, and to absorb the momentum. The Marica surge shaft will be one of the largest shafts of its type in the world
  • Excavation of the gate shaft at Tantangara is complete, with drill and blast work to excavate the transition tunnels linking it and the intake well advanced. The gate shaft is used to stop and start the flow of water into the headrace tunnel and power station for maintenance purposes or in the case of an emergency

Tunnel Boring Machines (TBMs) 

Florence

Florence is the TBM excavating the 16 kilometre headrace tunnel, which will connect the underground power station to the upper Tantangara reservoir

Following a seven-week operation to use ultra high pressure water jetting to remove very hard rock preventing the TBM from progressing, TBM Florence restarted excavation on Thursday 11 July

The Snowy delivery team expects highly variable ground conditions to continue ahead of TBM Florence, which will mean progress will continue to vary, particularly as the TBM navigates the curve leading to the main tunnel alignment

Lady Eileen Hudson

TBM Lady Eileen Hudson, which has completed the 2.8 kilometre main access tunnel to the power station, is now excavating the 6 kilometre tailrace tunnel, which will connect the underground power station to the lower Talbingo reservoir

The machine is progressing well and is approximately 3.0 kilometres into the tailrace tunnel

A conveyor belt extension and service modifications have recently been carried out so excavations to join the tailrace tunnel with the Talbingo intake excavation can commence

Kirsten

Kirsten is the TBM excavating the 1.6km Inclined Pressure Shaft (IPS – connecting the underground power station to the headrace tunnel that leads to the upper Tantangara reservoir), having already completed the 2.9km emergency, cable and ventilation tunnel

TBM Kirsten has installed 14 trial tunnel lining rings in the IPS using locally manufactured concrete segments specifically designed for the high water pressures that will be experienced in the IPS

Tunnelling of the IPS will be a pioneering engineering challenge, with the shaft’s incline reaching a steep 47 percent

News

TBM FLORENCE UPDATE

16/05/2024

Tunnel boring machine Florence has been ramping up excavating the Snowy 2.0 headrace tunnel, recently reaching 12 metres per day for a period.

With progress slowing in very hard rock on Wednesday 15 May, today (16 May) the Snowy 2.0 project team ceased excavation by the TBM due to rock pinching on the machine’s shield.

We are currently investigating the best way to relieve this pressure prior to recommencing excavation.

News

STUDENTS BENEFIT FROM SNOWY HYDRO LOCAL SCHOOL STEM FUND

26/06/2023

Hundreds of students across 18 Snowy Mountains schools will benefit from Snowy Hydro’s inaugural Local School STEM Fund program. The 2023 funding has been allocated to both primary and secondary from public and private schools to provide students with hands-on interactive experiences, challenging their creativity and critical thinking.

Through the program, Snowy Hydro has supported a varied range of science, technology, engineering and maths (STEM) initiatives, including an aquaponics project, 3D printers, a First Nations Science Camp, upgrades to equipment in science classrooms, development of a robotics club, enhancement of resources, the establishment and expansion of school programs and clubs, and the launch of various projects such as a sustainable garden and a township design. 

Snowy Hydro CEO Dennis Barnes said the collaboration with local schools will encourage and promote problem-solving skills for students, both in and out of the classroom and assist their career pathways.

“The funding is just one example of Snowy Hydro’s ongoing commitment to education and development in support of STEM, particularly among our local communities,” Dennis said. 

The real-world application of STEM allows students to interact with the subject material and develop a diverse range of skill sets. By seeing the outcomes of STEM throughout their lives and assessing the outcomes for themselves, their schools, community and surrounding environments, a unique and engaging learning space is created. 

Dennis said he was proud to announce the Local School STEM fund was “supporting schools in 10 locations, providing approximately $160,000 of funding to contribute to the growth of local students.” 

The outcomes of the funded initiatives will assist students with the understanding of sustainability, combine ancient knowledge and modern technology, build on existing STEM skills, develop critical thinking, strengthen student confidence and promote the balance of research and design. 

To further engagement and involvement with education, Snowy Hydro is committed to continuing this beneficial program. The next round of applications will open in February 2024.

For more information about Snowy Hydro’s Local School STEM Fund visit:

https://www.snowyhydro.com.au/local-school-stem-fund-2/

News

SNOWY 2.0 RENEWABLE ENERGY PROJECT – FIND OUT MORE!

06/02/2023

Snowy 2.0, a huge pumped-hydro expansion of the mighty Snowy Scheme, is at the heart of Australia’s transition to a renewable energy future and this is your chance to find out more about the project at local information sessions.

Snowy Hydro will host the Snowy 2.0 community information sessions starting from Thursday 9 February, providing locals with opportunities to be updated, ask questions and provide feedback.

Hear from the Snowy 2.0 project team about:

  • Current project activities and news;
  • Traffic management and road safety initiatives;
  • Accommodation, recreation access and other local issues;
  • Jobs and training on Snowy 2.0.

New Snowy Hydro CEO Dennis Barnes said construction of Snowy 2.0 was providing significant economic and social benefits right across the region.

“There are 2,200 people employed on the project and hundreds of millions of dollars are being invested locally, so it continues to be a very exciting time for communities throughout the Snowy Mountains,” Mr Barnes said. “I encourage everyone to come along to one of our sessions to hear the latest about Snowy 2.0, discuss any local concerns that you may have and answer your questions.”

Hosted by Snowy Hydro, the sessions will be attended by representatives from Future Generation Joint Venture, our Snowy 2.0 contractor building Snowy 2.0.

Talbingo and Tumbarumba will be drop-in sessions, with the chance to speak one-on-one with project team members, while there will be a formal presentation followed by community Q&As in Tumut, Cooma and Adaminaby.

Community information sessions schedule:

Thursday 9 February Talbingo shops 11.00am-2.00pm
Thursday 9 February Club Tumut 6.00pm-7.30pm
Friday 10 February Near Tumbarumba IGA, The Parade 11.00am-2.00pm
Tuesday 28 February Cooma Ex-Services Club 6.00pm-7.30pm
Wednesday 1 March Adaminaby Bowling Club 6.00pm-7.30pm

News

Snowy Hydro and SMEC reunite for Snowy 2.0

11/05/2017

Snowy Hydro Limited and the Snowy Mountains Engineering Corporation Australia (SMEC) will join forces once again, this time to carry out the feasibility study into the potential expansion of the Snowy Scheme’s pumped hydro storage capability.

Snowy Hydro and SMEC have a long association and worked together from the earliest days to develop the iconic 4,100 megawatt (MW) Snowy Mountains Hydro-Electric Scheme under the auspices of the Snowy Mountains Hydro-Electric Authority, established in 1949.

Selected through a tender competitive process which attracted interest from a field of world-class engineering firms, SMEC has now been appointed as the lead consultant engineer for the feasibility study into the first major expansion of the Scheme since construction days.

Snowy Hydro CEO Paul Broad said “SMEC was the obvious choice to partner with us on the study, given we share the same DNA. It really is a case of getting the band back together. The task now will be to bring together our best and brightest to revisit some of the visionary proposals developed over many years by the talented men and women who built the Scheme.”

The feasibility study will first review existing proposals to expand pumped hydro storage on the Snowy Scheme, many of which have existed since the 1960s. Under the most prospective proposal, up to 2,000 MW of hydro-electric energy could be added to the grid to act as rapid response back-up during periods of high demand and fill the gaps in energy supply caused by the growth in intermittent renewables and the exit of thermal baseload power.

The pumped hydro capability means the water utilised for electricity generation can be recycled to provide supply when it’s needed most, with no impact on the Scheme’s ability to continue to supply valuable water to irrigators in the food bowl of south-eastern Australia.

“This project has the potential to deliver one of the largest pumped hydro schemes in the world and underscores the importance of the Scheme’s existing role as the battery of the National Electricity Market.”

“While it has long been an Australian engineering icon, the importance of the Snowy Scheme’s role as the battery storage of the NEM will only become more critical as we move to a low carbon economy. The reliable, fast-start Scheme can help to responsibly manage the exit of baseload thermal power and the rise of intermittent renewables.

“As we move through the feasibility study phase, we will gain greater clarity around the technical and engineering requirements for the expansion as well as costs and timeframes for its construction”, Mr Broad said.

SMEC CEO Andy Goodwin said “Snowy Mountains are part of our namesake and the backbone of our heritage, so the chance to be involved in this project again is a unique ‘twice-in-a-lifetime’ opportunity, both for our organisation and those engineers who worked on the original scheme.

The Snowy 2.0 project will provide us with new design challenges from its predecessor and we’ve created a team of our most experienced specialists to deliver the feasibility stage.

We’re honoured to be part of the project and looking forward to resuming our presence within the Cooma community again.”

SMEC’s appointment will deliver significant benefits to the local Snowy Mountains community. As part of its commitment to this project, SMEC will reopen its previous offices in Cooma, which will see more than 30 staff permanently based in the town.