News

SNOWY 2.0 PROJECT UPDATE – JUNE 2023

26/06/2023

In the June update of the pumped-hydro expansion of the mighty Snowy Scheme, Snowy 2.0’s Alex Woschitzka explains construction progress at the massive Talbingo and Tantangara intakes. The project’s Quality Coordinator also checks in on the transformation of a narrow fire trail through steep terrain into a road suitable for heavy vehicles.

Significant progress has been made at the Talbingo intake, where water will exit the tailrace tunnel when Snowy 2.0 generates power. This is also where water enters the tunnel for pumping.

Construction teams have moved more than 310,000 cubic metres of earth to date, about half the total amount that will need to be moved. More than 24,000 metres of rock bolts have been installed and 8,300 square metres of shotcrete sprayed to support the wall.

As part of quality assurance, the shotcrete must be tested for compressive strength. Samples are taken from the truck and also cored from the face to ensure it meets the intended strength requirements. For the rock bolts, pull-testing is conducted to ensure they have been correctly installed, and meet the design and quality requirements. 

When completed, the total height of the Talbino intake excavation will be 104 metres, with about 31 metres of that below the water level. The concrete intake structure will be an impressive 50 metres in height.

Construction is well underway on an internal access road through mountainous terrain. With the help of Snowy 2.0 subcontractor Leed, a narrow fire trail will be widened into a six-kilometre road to enable heavy vehicles to access a rock emplacement area on Talbingo Reservoir.

Works began from both ends across very challenging terrain, achieving a major milestone recently when the two pioneering fronts joined across the Middle Creek cliffs. A temporary bridge with a 36-metre span has been installed across Middle Creek and is capable of supporting a fully-loaded 80-tonne dump truck.

In another milestone achieved in June, stage one earthworks have now been completed at the Tantangara intake. The first stage involved excavation of about 205,000 cubic metres of earth with a further 78,000 cubic metres of drilling and blasting earthworks expected in the next stage.

To support the excavation, more than 18,000 metres of rock bolts have been drilled and installed, and approximately 6,100 square metres of shotcrete sprayed. The excavation is currently about 26 metres deep and will be extended to a total depth of 55 metres.

Tantangara intake is where water will enter the headrace tunnel when the Snowy 2.0 power station is in generation mode. When in pumping mode, water will exit through the intake and fill Tantangara Reservoir. 

News

SNOWY 2.0 PROJECT UPDATE – MAY 2023

30/05/2023

May was a milestone month for the Snowy 2.0 team with the completion of the emergency, cable and ventilation tunnel, or ECVT – another vital step in the construction of Snowy Hydro’s new pumped-hydro expansion megaproject.

Snowy 2.0 senior project manager Rodd  Brinkmann explains the next stage of the project from his base at Lobs Hole, as preparation for excavation for the underground power station cavern gets underway.

The ECVT is a 2.93 kilometre tunnel that runs adjacent to the main access tunnel and provides alternate access to the site of the underground power station. Tunnel boring machine (TBM) Kirsten recently completed excavation of the ECVT and will soon start tunnelling the inclined pressure shaft. This very steep shaft links to the headrace tunnel from Tantangara Reservoir. 

TBM Kirsten will need to undergo modifications to excavate the 25-degree incline, including installation of a screw conveyor to extract excavated rock from the cutterhead to a sandwich conveyor system. With such a steep incline, construction of the 1.45km shaft with its concrete segment-lined tunnel, will be a world first. 

In the main access tunnel, or MAT, construction of cross passages and construction access tunnels is well underway with 850 metres of drill and blast tunnel excavation completed. Of the five cross passages linking the MAT and the ECVT, two are fully excavated and waiting on breakthrough into the ECVT.  Key construction tunnels are also being excavated to provide access to the machine hall, transformer hall and the top of the tailrace surge shaft. 

Workers have reached the main cavern areas from both ends and will soon commence excavation and support of the cavern crowns or ceilings of the power station halls. The excavation sequence of the cavern crowns is critical, as the in situ rock mass will relax and move inwards as the excavated void increases. These movements will be closely monitored during the process. Geotechnical drilling and plate load tests will measure and confirm the characteristics of the rock geology around the power station.

Dynamic 3D models of the power station caverns are also being used. 3D models are created using digital engineering to transform 2D design drawings and are displayed in the state-of-the-art immersive theatre at Snowy Hydro’s Discovery Centre in Cooma, where Snowy 2.0 engineers can collaborate with power station design experts from around the world. Once construction is complete, the detailed 3D models will be a valuable tool for asset maintenance. 

With so much activity in the tunnels, the current Snowy 2.0 underground workforce will increase by another 200 people in the coming months.  

News

SECOND TUNNEL EXCAVATED FOR SNOWY 2.0

22/05/2023

The Snowy 2.0 pumped-hydro mega project has achieved another important construction milestone, with a second tunnel excavation completed at Lobs Hole in the Snowy Mountains.

The 2.93-kilometre emergency, cable and ventilation tunnel (ECVT) has been excavated and fully lined with 13,140 locally-manufactured concrete segments by tunnel boring machine (TBM) Kirsten. This achievement follows the excavation of the adjacent main access tunnel (MAT), which was completed in October 2022.

Snowy Hydro CEO Dennis Barnes said Snowy 2.0 was continuing to make solid progress, with around six kilometres of tunnelling by TBMs completed and drill and blast excavation of the power station cavern about to start.

“We are extremely pleased the ECVT excavation has been completed and the whole project team is excited to be moving into the next critical phase of construction. Our huge power station cavern will be located about 800 metres underground and will be one of the largest and deepest in the world.

“We are also using drill and blast methods to construct cross passages linking the ECVT with the MAT.

“Meanwhile TBM Kirsten, which is setting a global standard in TBM technology, is being modified to carry out another very specific task – to excavate the inclined pressure shaft and line it with specially-designed and locally manufactured concrete segments.

“The shaft is 1.45km long and excavating a segment lined tunnel of this length at a very steep 47% incline using an 11-metre diameter TBM is without precedent internationally.” 

Modifications to Kirsten include altering the levels of the TBM’s tanks and mechanical equipment so they remain horizontal when travelling up the incline, and converting the walkways into steps and ladderways. 

Also being installed is a screw conveyor to extract excavated rock from the cutterhead to a sandwich conveyor system with face-to-face rubber belts that help constrain the crushed rock so that it can be transported down the steep slope without spillage.

Additional plant and equipment will also be installed in the ECVT tunnel to support the excavation activities including; an overhead crane, a conveyor transfer station, monorail manrider for personnel access and rack and pinion mechanism for plant access to the TBM, 

There is currently a project workforce of more than 2,700 across four major worksites building Snowy 2.0, a critically important, pumped-hydro expansion of the Snowy Scheme that will help underpin Australia’s transition to renewables.

ECVT fast facts

  • 2.93-kilometres in length
  • 10 metres internal diameter
  • Lined with 1,460 concrete rings with 9 segments per ring installed by TBM Kirsten
  • Precast segments are manufactured locally in Cooma
  • ECVT has five cross-passages linking it to the adjacent main access tunnel
  • Provides secondary access with clean air to the power station complex and will be used permanently for ventilation and high voltage cables, and intermittently for general access and maintenance.
News

SNOWY 2.0 PROJECT UPDATE – APRIL 2023

09/05/2023

In our April update of the Snowy 2.0 pumped-hydro project, Snowy Hydro CEO Dennis Barnes pays tribute to Alan Machon, who tragically died in a road accident. Alan was a member of the Future Generation team working to deliver Snowy 2.0.

Out onsite, Snowy 2.0 Integration Manager, Paul Smith, joins us from the recently completed Ravine Road, we meet the captain of the Lobs Hole Emergency Response Team and we stop by the Talbingo adit to check on progress of TBM Lady Eileen Hudson’s reassembly in readiness for her second major tunnelling task.

The construction of Ravine Road was one of the first projects undertaken for Snowy 2.0. Originally little more than a dirt track, the main access into the Lobs Hole site has been transformed to provide safe all-weather access for project trucks and light vehicles.

The steep, winding 15-kilometre road is now two lanes wide and in March 2023 it was fully sealed with line marking, snow poles and reflective markers installed to help guide road users in low visibility conditions. With an 850-metre elevation difference from top to bottom, the upper section of Ravine Road is above the snow line.

Areas disturbed during construction are being reinstated and the rehabilitation process is underway. When the Snowy 2.0 project is complete, the general public will be able to use Ravine Road to access a popular camping area once restricted to 4WD vehicles.

At the Talbingo adit, tunnel boring machine Lady Eileen Hudson is being reassembled in preparation for excavation of the tailrace tunnel. New components including the cutterhead and tailskin will soon be lifted into the TBM cradle to be attached to the shields and main drive. After completing the excavation of the main access tunnel, the TBM gantries were removed using self-propelled mobile transporters and will be attached to the machine so it can begin excavating the six-kilometre tunnel. The vertical conveyor belt stacker has been assembled, construction of the water treatment plant is progressing and the grout plant will soon be commissioned.

Snowy 2.0 emergency response teams, or ERTs, regularly conduct training to keep the onsite workforce safe and to prepare for possible emergencies such as vehicle rescues and bushfires.

Future Generation’s Lobs Hole ERT captain, Drew Butters, is a Snowy Mountains local who has worked on the project for three years. He has had a life-long association with emergency response and fire fighting in the Rural Fire Service and is currently the Adaminaby RFS captain.

ERTs are trained to deal with bushfires, general firefighting, emergency response and rescue. Emergency Response Teams have a small crew with experienced full-time members, plus a number of volunteers at each work site.

News

SNOWY 2.0 – PROJECT UPDATE

03/05/2023

Snowy Hydro’s management team is working towards resetting the delivery timeline and budget for the Snowy 2.0 project with its principal contractor, Future Generation Joint Venture (FGJV), as part of an ongoing project review. 

The reset will ensure this critically important clean energy infrastructure project is placed on a robust and sustainable footing for FGJV to progress the schedule in a realistic and productive manner. 

While significant progress has been achieved by FGJV on Snowy 2.0, there are delays to Snowy 2.0’s contracted schedule and likely cost impacts beyond the contingency allowed, which remain under review by Snowy Hydro. 

There are four broad categories of factors contributing to schedule delays and likely cost increases: 

  • the mobilisation and resourcing implications of the COVID-19 pandemic; 
  • the effect of global supply chain disruption and inflation impacting the cost and availability of a skilled workforce, materials, and shipping; 
  • a number of design elements requiring more time to complete due to their technically complex nature, with the final design now being more expensive to construct; and  
  • the impact of variable site and geological conditions, with the most impactful being the soft ground encountered that is delaying tunnel boring machine (TBM) Florence’s progress at Tantangara.  

Snowy Hydro anticipates that the timeline for full commercial operation is delayed by a further 12-24 months from the current publicly released dates:

MilestoneEarliestLatest
First Power June 2027 – December 2027June 2028 – December 2028
Commercial operation of all units December 2028 December 2029

Snowy Hydro expects more detail on the budget implications of the project reset around July 2023, and this will be clearly communicated with key project stakeholders.  

Snowy Hydro CEO Dennis Barnes said: 

“Since joining Snowy Hydro earlier this year I have focused on ensuring our major projects are placed on a realistic and sustainable footing, while maintaining construction progress.  

“This project is critically  important to the transition of Australia’s electricity grid and it’s crucial that we are working to a safe, efficient and realistically achievable timeframe to enable orderly planning for all our stakeholders. I am committed to being transparent about our progress and how we are proactively managing the inevitable issues and challenges that arise in a complex project like this. 

“While many other major infrastructure projects have been impacted by the same challenges, Snowy 2.0 continues to make positive progress.

“Snowy 2.0 is providing significant employment and economic benefits both regionally and domestically. There are currently over 2,400 people employed on the project and thousands more jobs generated indirectly through supply chains and support services.

“TBM Kirsten has tunnelled 2.9 km to reach the underground power station cavern complex and we now have access to this site from both ends. We shortly expect to commence the 6km tailrace tunnel that will feed into Talbingo Reservoir and the excavation of intakes at Talbingo and Tantangara are proceeding very well.”

News

SNOWY 2.0 TUNNELLING UPDATE

01/03/2023

Snowy 2.0 is a critically important, pumped-hydro expansion of the Snowy Scheme that will help underpin Australia’s transition to a renewable energy future.

Construction of Snowy 2.0 continues to make progress across multiple worksites. At Lobs Hole, tunnel boring machine (TBM) Lady Eileen Hudson has completed excavation of the 2.7km main access tunnel and TBM Kirsten is almost finished excavating the adjacent 2.9km emergency, cable and ventilation tunnel (ECVT).

At Tantangara, the project team is currently conducting works to stabilise encountered soft ground and enable TBM Florence to restart excavating the headrace tunnel.

TBM Florence has tunnelled about 150 metres and is currently located at a depth of approximately 30 metres below ground. A surface depression recently emerged in the ground above TBM Florence, which has temporarily delayed progress on this particular worksite. The depression is approximately nine (9) metres deep and continues to be monitored. 

Importantly, the integrity of the tunnel, which is supported by a concrete lining and steel ribs, has not been compromised, and nor has the capacity of the TBM. The project team has paused the machine until about 10-15m of weak material in front of it is stabilised, prior to striking hard rock, when we expect normal tunnelling to resume. 

Snowy 2.0 principal contractor Future Generation Joint Venture (FGJV) is drilling probe holes through the front of the excavation to understand the ground conditions immediately ahead of the TBM. Grout is injected in front of the excavation to improve any weak zones and limit any water flows. Grouting is well underway from TBM Florence, with 20 grout holes drilled to date in the current location.

FGJV is currently installing a slurry plant for the TBM that will mean the machine can switch from open excavation to a closed, pressurised mode. This will deliver stable excavation and efficient progress through the softer ground conditions, while enabling the TBM to switch back to open mode when in harder rock.  

Stage two of the works to stabilise the ground in front and above the machine will involve ground improvement from the surface. Once the area is grouted, the depression will be backfilled and revegetated.

Snowy Hydro has been responsibly operating the Snowy Scheme in Kosciuszko National Park for decades and remains committed to careful and safe management of this tunnelling challenge in a sensitive environment.

The Snowy 2.0 workforce of more than 2,200 is continuing to achieve milestones across a range of work fronts as they build the huge pumped-hydro expansion of the Snowy Scheme.

At Lobs Hole, in the main access tunnel, works are continuing on multiple drill and blast cross tunnels. These will link with the ECVT, where TBM Kirsten has tunnelled 2.8km and has reached the site of the underground power station cavern complex. This is a great milestone for Snowy Hydro as we now have access to the excavation site from both ends of the cavern, which will be one of the largest and deepest in the world. 

TBM Kirsten is setting a global standard in tunnel boring technology, just as the original Snowy Scheme developed rock bolting techniques that are still used throughout the world today. The machine will soon be modified to excavate the inclined pressure shaft on a steep uphill angle. Modifications include altering the levels of the TBM’s tanks and mechanical equipment so they are level when travelling up the 25-degree incline, and converting the walkways on the machine’s sides into steps and ladderways.   

Meanwhile TBM Lady Eileen Hudson is being reassembled at the Talbingo adit with some new components including a cutterhead and shields. It will be launched into the mountain later this year to excavate the 6km tailrace tunnel, which will feed into Talbingo Reservoir.

Excavation of intakes at Talbingo and Tantangara is advancing steadily, along with the giant surge shaft on the Marica plateau that is already excavated to a depth of more than 20m.  

Despite the ongoing challenges faced by all large infrastructure projects, Snowy 2.0 continues to achieve progress across a large number of remote work fronts. 

Snowy Hydro remains fully committed to ensuring the local community and stakeholders are kept updated on this pumped-hydro mega project that will provide the National Electricity Market with 2,000 megawatts of on-demand generating capacity and a huge 175 hours of energy storage.

Caption: 3D imagery of surface depression above TBM Florence at Tantangara, created using photogrammetry technology

Caption: Snowy 2.0 project overview.

Caption: Talbingo adit, where TBM Lady Eileen Hudson is being reassembled for excavation of the tailrace tunnel.

News

SNOWY 2.0 RENEWABLE ENERGY PROJECT – FIND OUT MORE!

06/02/2023

Snowy 2.0, a huge pumped-hydro expansion of the mighty Snowy Scheme, is at the heart of Australia’s transition to a renewable energy future and this is your chance to find out more about the project at local information sessions.

Snowy Hydro will host the Snowy 2.0 community information sessions starting from Thursday 9 February, providing locals with opportunities to be updated, ask questions and provide feedback.

Hear from the Snowy 2.0 project team about:

  • Current project activities and news;
  • Traffic management and road safety initiatives;
  • Accommodation, recreation access and other local issues;
  • Jobs and training on Snowy 2.0.

New Snowy Hydro CEO Dennis Barnes said construction of Snowy 2.0 was providing significant economic and social benefits right across the region.

“There are 2,200 people employed on the project and hundreds of millions of dollars are being invested locally, so it continues to be a very exciting time for communities throughout the Snowy Mountains,” Mr Barnes said. “I encourage everyone to come along to one of our sessions to hear the latest about Snowy 2.0, discuss any local concerns that you may have and answer your questions.”

Hosted by Snowy Hydro, the sessions will be attended by representatives from Future Generation Joint Venture, our Snowy 2.0 contractor building Snowy 2.0.

Talbingo and Tumbarumba will be drop-in sessions, with the chance to speak one-on-one with project team members, while there will be a formal presentation followed by community Q&As in Tumut, Cooma and Adaminaby.

Community information sessions schedule:

Thursday 9 February Talbingo shops 11.00am-2.00pm
Thursday 9 February Club Tumut 6.00pm-7.30pm
Friday 10 February Near Tumbarumba IGA, The Parade 11.00am-2.00pm
Tuesday 28 February Cooma Ex-Services Club 6.00pm-7.30pm
Wednesday 1 March Adaminaby Bowling Club 6.00pm-7.30pm

News

SNOWY 2.0 HEADRACE TUNNEL UPDATE

16/12/2022

Snowy 2.0 teams are monitoring a surface depression that has emerged above the headrace tunnel at Tantangara.

The integrity of the tunnel has not been compromised, and tunnelling is continuing while work to remediate the surface depression above tunnel boring machine (TBM) Florence is carried out. There is a safety exclusion zone around the surface depression.

Ensuring the safety of the Snowy 2.0 workforce and members of the public is the priority for Snowy Hydro and principal contractor Future Generation Joint Venture. 

The Snowy 2.0 teams are conducting geophysical investigations of the area and continuing grouting operations and probing from the TBM. 

As previously indicated, the ground conditions encountered by the TBMs on Snowy 2.0 have been highly variable, ranging from very loose, sandy ground to extremely hard rock in fluctuating groundwater conditions. 

TBM Florence is transitioning from soft material into harder rock conditions. 

News

MILESTONE FIRST TUNNEL COMPLETED FOR SNOWY 2.0

11/10/2022

Snowy Hydro is celebrating the completion of excavation for its first tunnel for Snowy 2.0, with the Lady Eileen Hudson tunnel boring machine (TBM) reaching the location of the new underground power station cavern.

The 11-metre diameter TBM has excavated 2.85km to create the main access tunnel at Lobs Hole in the Snowy Mountains, where a workforce of more than 2,200 people are building Snowy 2.0 – the 2,000 megawatt pumped hydro expansion of the mighty Snowy Scheme.

Snowy Hydro acting CEO Roger Whitby said the tunnelling achievement was a significant milestone, with Snowy 2.0 set to underpin the nation’s transition to renewables.

“Snowy 2.0 will not only provide on-demand, quick-start generating capacity for the National Electricity Market (NEM), but a massive 350,000 gigawatt hours of energy storage,” Mr Whitby said.

“This is our first new major tunnel excavation in decades, since construction of the original Scheme, and it gives us access to the site where we will create the enormous cavern 800m underground that will house our power station.

“The TBM Lady Eileen Hudson and our teams from Snowy Hydro and contractor Future Generation Joint Venture have done a great job to complete this critical tunnelling task.

“However, there’s no slowing down. Work across the project continues to move ahead rapidly and this tunnel boring machine is now being dismantled so it can be moved to the Talbingo adit where it will be reassembled with some new components for excavation of the 6km tailrace tunnel.”

While dismantling of the TBM conveyor belt gets underway in the main access tunnel, drill and blast activities are ongoing to excavate cross passages and tunnels to gain access to the power station complex, which will include a 251m-long, 52m-high machine hall cavern and 223m-long, 46m-high transformer hall cavern.

The new work fronts associated with the powerhouse will create further employment opportunities on this clean energy mega-project.

The Snowy 2.0 project will link Tantangara Reservoir (top storage) with Talbingo Reservoir (bottom storage) through 27km of tunnels and a power station with pumping capabilities.

This will enable water to be released for energy generation at times of peak demand and then pumped back to the top storage when there is excess renewable energy in the system, ready to generate again.

Main access tunnel fast facts:

  • 10 metres in diameter
  • Lined with 1,422 concrete rings installed by the TBM
  • Rings comprise 12,798 individual segments manufactured locally in Cooma
  • Has four cross-passages linking it to the adjacent emergency, cable and ventilation tunnel
  • Also has four cross tunnels and a turning bay to facilitate construction access around the power station complex
  • Provides pedestrian and vehicle access into the power station
News

TBM FLORENCE ON THE MOVE

05/10/2022

Tunnel boring machine (TBM) Florence continues excavating the Snowy 2.0 headrace tunnel at Tantangara following successful reinforcement works.

As anticipated, the ground conditions encountered by the TBMs on Snowy 2.0 have been highly variable, ranging from soft, sandy ground to extremely hard rock. 

The Snowy 2.0 teams have been working collaboratively to safely navigate the softer ground conditions experienced at Tantangara, including high groundwater inflows.

As part of the tunnelling process we probed in advance of the TBM, identifying the soft ground ahead, and then consulted with our expert design consultants to plan for stabilisation works. TBM Florence has been specifically designed to encounter these variable ground conditions.

Consolidation grouting around the perimeter of the headrace tunnel, and internally, the installation of steel ribs to reinforce the concrete segmental lining in the soft zone, have been carried out to ensure stability and manage groundwater inflows. Additional instrumentation to monitor ground performance has also been installed.  

Successful execution of the reinforcement works by Snowy 2.0 principal contractor Future Generation Joint Venture (FGJV) is enabling the TBM to carefully thrust off the segments and move forward.

Snowy Hydro expects variable and soft ground conditions to occur in sections of the very long 17-kilometre headrace tunnel. Further ground improvement works – a typical tunnelling process – will be carried out where required so the TBM can safely advance.

Snowy Hydro and its Future Generation Joint Venture partners are working towards the successful delivery of Snowy 2.0.

Click here for images of TBM Florence and the reinforcement works.

News

SNOWY HYDRO’s SNOWY 2.0 IS POWERING HEAD – FIND OUT MORE!

09/05/2022

With work on Snowy 2.0 powering ahead and three huge tunnel boring machines now in operation, now is a great time for community members to discover more about Australia’s largest committed renewable energy project at local information sessions being held throughout the Snowy Mountains.

Snowy Hydro will host the Snowy 2.0 community information sessions starting from Tuesday 10 May, providing locals with opportunities to be updated, ask questions and provide feedback.

Hear from the Snowy 2.0 project team about:

  • Current project activities and news;
  • Traffic management and road safety initiatives;
  • Accommodation, recreation access and other local issues; 
  • Jobs and training on Snowy 2.0.

Snowy Hydro CEO Paul Broad said construction of the Snowy 2.0 pumped-hydro expansion of the mighty Snowy Scheme was providing significant economic and social benefits right across the region.

“There are 1,800 people employed on Snowy 2.0 and tens of millions of dollars are being invested locally, so it continues to be a very exciting time for communities throughout the Snowy Mountains,” Mr Broad said.

“I encourage everyone to come along to one of our sessions to hear the latest about Snowy 2.0 and learn more about all of the training and work opportunities with the project. 

“We’re keen to hear your views about Snowy 2.0, discuss any local concerns that you may have and answer your questions.”

Run by Snowy Hydro, the sessions will be attended by representatives from Future Generation, the joint venture partnership managing Snowy 2.0 jobs, procurement and subcontracting.

There will be a formal presentation and Q&As at the sessions, plus the chance to speak one-on-one with project team members while enjoying light refreshments. 

Community information sessions schedule:

Date Town and locationTime
Tuesday 10 May 
Wednesday 11 May 
Cooma Ex-Services Club
Adaminaby Bowling Club
6-7.30pm
6-7.30pm
Tuesday 17 May 
Wednesday 18 May  
Thursday 19 May
Cafe Nest, Tumbarumba
Club Tumut
Talbingo Country Club
6-7.30pm
6-7.30pm
6-7.30pm
News

SNOWY 2.0 POWERING AHEAD WITH COMMISSIONING OF TUNNEL BORING MACHINE FLORENCE

22/03/2022

Snowy Hydro and members of the local community have today come together to celebrate the commissioning of the third and final tunnel boring machine (TBM) for Snowy 2.0, Australia’s largest renewable energy project.

The 143 metre-long TBM Florence is one of a trio of technologically-advanced machines excavating more than 27 kilometres of waterway tunnels as part of Snowy 2.0, the huge pumped-hydro expansion of the iconic Snowy Mountains Scheme that is ensuring Australia’s secure and reliable transition to renewables.

Snowy Hydro Managing Director and CEO Paul Broad joined Snowy Mountains community members and representatives from Snowy 2.0 principal contractor Future Generation Joint Venture for a celebration event and ribbon-cutting at Tantangara, where TBM Florence is being launched to excavate the headrace tunnel.

Mr Broad said it was a wonderful experience sharing a significant project milestone with the community, former Snowy Scheme workers and local school children and businesses.

“We want to thank the local community for their support. It’s great knowing that this massive project is delivering thousands of jobs, many training and apprenticeship opportunities for workers, and a major economic boost for the Snowy Mountains region and beyond,” Mr Broad said.

“The progress we’re making on Snowy 2.0 is terrific. The other two TBMs, Lady Eileen Hudson and Kirsten, are already powering ahead excavating the main access tunnel and emergency, cable and ventilation tunnel at Lobs Hole, so we’re delighted to be starting this very long and deep headrace tunnel from Tantangara.

“Watching TBM Florence’s big blue cutterhead spin today alongside people who helped build the original Scheme highlights the pride we at Snowy Hydro have in our pioneering past and how exciting the renewable energy future is with Snowy 2.0.”

There are almost 1,800 people currently working on Snowy 2.0, including hundreds of locals, with the project generating about 4,000 direct jobs and many more in the supply chain.

Snowy 2.0 will deliver 2,000 megawatts of pumping and generating capacity and 175 hours of storage – enough to power 500,000 homes simultaneously – which will underpin thousands of megawatts of intermittent renewables. 

Named after Australia’s first female electrical engineer, Florence Violet McKenzie (1890-1982), TBM Florence is set to excavate 14.9 kilometres of the 17km headrace tunnel. The 11-metre diameter Herrenknecht-designed machine has been purposely designed to manage hazardous dust and poor ground conditions while tunnelling up to 450 metres underground.

TBM Florence was named by local Berridale student Riley Douch as part of the Snowy 2.0 Tunnel Boring Machine Naming Competition, which highlighted ground-breaking Australian women in science, technology, engineering and maths (STEM).
For more information about Snowy 2.0 visit snowyhydro.com.au