News

HUNTER POWER PROJECT – PLANNING MODIFICATION AMENDMENT

03/10/2024

Hunter Power Project (HPP) is set to begin operations in December 2024 with one generator running on diesel during the testing and commissioning phase. 

The second unit and gas introduction will follow shortly, with full operations expected within a few months. 

While the project’s planning modification has proposed increasing diesel operating hours to 1,100 per unit for 2025, Snowy Hydro does not currently expect HPP to operate entirely on diesel in 2025. The purpose of the modification is to provide for the current anticipated completion of the gas pipeline to March 2025 plus appropriate program contingency to ensure the power station can still generate energy in the event of any further delays to the gas pipeline or to the project’s commissioning program.

HPP’s gas pipeline is being delivered by APA Group and is independent of Snowy Hydro’s delivery of the power station. 

Snowy Hydro has updated some of the information submitted to the NSW Department of Planning, Housing and Infrastructure. Previously some of the information was inaccurate and did not accurately reflect our intentions around contingency planning being one of the drivers of the modification.

Once fully operational, HPP will primarily run on gas, using diesel as backup. Gas remains crucial for meeting peak demand and supporting Australia’s renewable energy transition.

News

SNOWY HYDRO STATEMENT – TRAGIC SNOWY MOUNTAINS HIGHWAY TRUCK ACCIDENT

24/04/2023

Snowy Hydro extends its deepest condolences to the family, friends and workmates of a man involved in a single vehicle crash on the Snowy Mountains Highway today.

NSW Police has confirmed that the driver of the vehicle, a Snowy 2.0 project truck, did not survive the accident.

Snowy Hydro CEO Dennis Barnes said the incident was incredibly distressing. “This is a tragic event and we are supporting our Snowy 2.0 Principal Contractor, Future Generation Joint Venture (FGJV), our teams and all those impacted in the community at this very sad and difficult time.”

The welfare of Snowy 2.0 workers is our immediate priority and project operations have ceased until the night shift on Tuesday 25 April.

News

SNOWY HYDRO RESPONDS TO ABC 7.30

12/02/2023

The National Electricity Market (NEM) is in the process of fundamental transformation – from baseload coal with some peaking assets to a complex, highly interconnected system with variable renewable energy backed by firming and storage. Snowy 2.0, with its massive 2,000 megawatts of generation and 350,000 megawatt hours of energy storage, is critical to Australia’s decarbonisation as it will help underpin the rapid transition to a fully renewable future.

Solid construction progress is occurring across a large number of Snowy 2.0 work fronts. At Lobs Hole, the Talbingo intake is well underway, the main access tunnel excavation by tunnel boring machine (TBM) Lady Eileen Hudson is completed and the emergency, cable and ventilation tunnel excavation by TBM Kirsten is close to completion.

Across the project, and as anticipated, the ground conditions encountered by the Snowy 2.0 TBMs are highly variable, ranging from soft, sandy ground to extremely hard rock. TBM Florence at Tantangara has been traversing a section of soft ground and is temporarily paused while plans to remediate a surface depression above the Tantangara adit (as reported on the Snowy Hydro website in December) are finalised. 

Complex and variable ground conditions are not unusual in such projects. Snowy Hydro and the Snowy 2.0 EPC contractor, Future Generation Joint Venture, are focused on delivering the project safely and in a manner respectful of the sensitive environment, while managing impacts caused by external events including COVID-19, high material costs, global supply chain constraints, labour shortages across the Australian construction industry and ongoing weather conditions.

Commercial claims on construction projects are also common. As with other major infrastructure projects, Future Generation Joint Venture has experienced significant impacts from COVID, resourcing and supply chain challenges. Claims submitted to Snowy Hydro by the contractor continue to be assessed and paid appropriately, in accordance with contractual requirements. 

Snowy Hydro’s BBB+ credit rating was reaffirmed by Standard & Poors in December. The move from stable to negative outlook primarily reflects forecast depressed earnings in FY2023  resulting from the critical role the company played during volatile market conditions in May to June 2022 and the potential project cost escalations for Snowy 2.0 and the Hunter Power Project owing to general market inflation and global supply chain issues. As Snowy’s earnings profiles become more certain, S&P will continue to monitor and assess Snowy’s outlook.  At this stage, there are no current plans for any additional Shareholder equity beyond the current arrangements for Snowy 2.0 and Hunter Power Project.  

The Snowy 2.0 budget is $5.9 billion and remains unchanged since the project approval. Snowy Hydro will continue to assess inflation and global supply chains moving forward.

News

SNOWY HYDRO STATEMENT ON CLOUGH – UPDATED 16 December 2022

16/12/2022

Snowy Hydro welcomes the announcement by Webuild that it has reached an agreement with Clough Limited administrators to acquire Clough’s share of the Snowy 2.0 project contract and its related workforce.

Our priority remains ensuring the wellbeing and continuity of Clough’s workers on the project and the smooth progress of Snowy 2.0 construction.

We will continue to work closely with Webuild and the administrators throughout the acquisition process.    

News

SNOWY HYDRO STATEMENT ON CLOUGH – UPDATED

09/12/2022

Snowy Hydro is aware of the announcement regarding the financial status of Clough, the Snowy 2.0 Future Generation Joint Venture partner.  

Snowy Hydro notes Clough’s earlier financial disclosure indicates financial issues with projects separate and unrelated to Snowy 2.0. 

As work continues on Snowy 2.0, Snowy Hydro’s first priority is ensuring the wellbeing and continuity of Clough’s workers on the project.

Snowy Hydro welcomes the immediate funding provided by joint venture partner Webuild for the payment of wages to all Clough employees working on the Snowy 2.0 project.

We are working closely with the joint venture to ensure construction on the project progresses smoothly.  

Resolving Clough’s future through the voluntary administration process will take some time and Snowy Hydro will support this process wherever possible.

News

SNOWY HYDRO STATEMENT ON CLOUGH

06/12/2022

Snowy Hydro is aware of the announcement regarding the financial status of Clough, the Snowy 2.0 Future Generation Joint Venture partner.

Snowy Hydro notes Clough’s earlier financial disclosure indicates financial issues with projects separate and unrelated to Snowy 2.0.

As work continues on Snowy 2.0, Snowy Hydro’s first priority is ensuring the wellbeing and continuity of Clough’s workers on the project.

We are working closely with the joint venture to ensure construction on the project progresses smoothly.

Resolving Clough’s future through the voluntary administration process will take some time and Snowy Hydro will support this process wherever possible.

News

STATEMENT ON SNOWY HYDRO’S LEADERSHIP

26/08/2022

Paul Broad, Managing Director and CEO of Snowy Hydro, has offered his resignation.

For more than 70 years Snowy Hydro’s success has been founded on strong and stable leadership. Paul Broad is no exception to that rule.

Since 2013, Paul has led organisational expansion and innovation, transforming Snowy Hydro into a dynamic and integrated energy business. 

Externally Paul is best known by the Australian public for his leadership on Snowy 2.0 and leading Snowy Hydro’s expansion into retail and renewable energy. 

Snowy 2.0 is a nation-defining and world-leading infrastructure project. It will underpin the transition to a decarbonised National Electricity Market and now employs more than 2,000 people, generating huge economic uplift in the Snowy Mountains. 

Under Paul’s leadership, the first Snowy Hydro renewable energy procurement program began in 2018 and has grown to encompass 12 contracts with wind and solar projects totalling 1.3 gigawatts of energy generation. 

For the local community and Snowy Hydro team, Paul will remain best-known for his extraordinary leadership during incredibly challenging periods, including the 2019/2020 bushfires and the COVID-19 pandemic. 

Paul’s firm commitment to the safety, health and well-being of the Snowy Hydro family will remain a cornerstone of his legacy. 

The Snowy Board will now commence a process to identify new leadership. Roger Whitby, Chief Operating Officer, will lead the organisation on an interim basis, with support from Paul to facilitate a smooth transition. 

News

SNOWY HYDRO’S ENERGY CRISIS RESPONSE

29/07/2022

As the energy crisis in the National Electricity Market (NEM) continues to unfold, Snowy Hydro is being called on more than ever to keep the lights on and prices down. Snowy’s role as the NEM’s ‘insurance policy’, providing on-demand energy generation during the crisis, has significantly impacted our business.

CEO and Managing Director Paul Broad said Snowy Hydro strongly rejected commentary suggesting it is to blame for recent high prices in the NEM.

“These comments misunderstand the cause of the energy crisis, as well as Snowy Hydro and the nature of its generation assets,” he said.

Snowy Hydro is a relatively small supplier of energy owing to the fact that its principal source of fuel (water) is limited. In most years Snowy Hydro supplies between 2-4% of the total energy generated in the NEM, operating at critical times of peak demand and when there are unplanned baseload outages. 

The current crisis has arisen due to shortfalls from suppliers of bulk energy, including coal, wind and solar. To help manage this shortfall, Snowy Hydro has operated its assets at record levels, effectively as a baseload generator. 

“To blame high prices on Snowy Hydro for stepping into the void left by bulk energy providers is absurd,” Mr Broad said.

“Were it not for the actions of Snowy, prices would have been significantly higher. Our teams have worked tirelessly and closely with AEMO, the market operator, throughout this challenging period.

“In May this year, generation from the Snowy Scheme was almost double the previous monthly record. This was essential for maintaining security of supply in the NEM, but it is not sustainable. 

“Snowy’s ability to operate in this manner is constrained by its fuel scarcity – we don’t have enough water to manage the ‘energy gap’ from other generators for extended periods,” Mr Broad said.

Snowy Hydro’s water resources must be carefully allocated to the highest value periods in order to keep the lights on. In other words, hydro generation has a high opportunity cost.

It is wrong to suggest that high prices could have been avoided, or that Snowy Hydro should have offered its generation at lower prices. Doing so would have caused our hydro assets to be dispatched ahead of other forms of generation with a cheaper cost of fuel. Not only would this not have made economic sense, it would have left the company unable to respond to critical demand peaks this winter and summer, further increasing the risk of blackouts.

The implication that Snowy Hydro enjoyed a financial windfall as a consequence of the crisis is also inaccurate. Most energy dispatched in the NEM is pre-sold to customers under short or long-term contracts. This is essential for stabilising the cash flow of generators and retailers and is part of the market design. It also means that a narrow focus on price outcomes in the NEM reveals little about generator profitability. 

The steps taken by Snowy Hydro to help keep the lights on – depleting its reserves of available water – have in fact been detrimental to the company’s financial and risk position. Snowy Hydro rejects any suggestion it has been ‘profiteering’ from the crisis, or has in any way exacerbated it. 
Snowy Hydro will remain focused on ensuring security of supply for the NEM during this challenging period.

News

Statement from CEO Paul Broad on COVID-19 case

30/03/2020

As a provider of essential services we are well prepared to operate through COVID-19.  For weeks now we’ve had extensive measures in place to keep the lights on and progress Snowy 2.0 as safely and responsibly as possible.

On Thursday last week we were notified of a positive COVID-19 test result involving a Snowy Hydro employee who went immediately into self-isolation after returning from an overseas holiday.

As per Snowy’s strict and proactive COVID-19 protocols, the individual went into self-isolation immediately upon returning to Australia and did not come into contact with anyone. The employee was later tested following the development of a mild cough.

NSW Health Department has concluded that the employee has not transmitted the virus to any other person. In this case, the risk measures implemented by Snowy Hydro weeks ago were very effective and the staff member will remain in isolation until he is medically cleared.

Snowy Hydro continues to strictly enforce all of its COVID-19 safety and risk measures. We are operating at full capacity, Snowy 2.0 is full steam ahead and we continue to invest locally, supporting jobs and working with local businesses and suppliers.

News

Snowy Hydro COVID-19 response

27/03/2020

Snowy Hydro today welcomed the Australian Energy Regulator’s principles to protect customers and small businesses facing financial hardship resulting from COVID-19.

Snowy Hydro’s CEO, Paul Broad said through its retail brands Red Energy and Lumo Energy, is continuing to lead the industry on assisting customers experiencing financial hardship.

“We have always put our customers first.  Last week we introduced a range of protective measures, similar to our recent response to bushfires and the ongoing drought. These included: 

  • Since 20 March 2020, all disconnections for customer and small business debt have ceased. 
  • 300 customer solutions consultants are taking calls and additional resourcing has been identified to support the customer care team who deal with customers experiencing financial difficulty.
  • As per current policies of the Retail businesses, there will be no interest charged on debt.
  • Both Red Energy and Lumo Energy websites and digital channels have been updated to emphasise that customers impacted by COVID-19 should call us and that customer assistance is available. 


“Red and Lumo’s customer solutions team has already seen a significant increase in calls from customers reporting job losses and seeking assistance.  We have deployed extra staff, many working overtime to cope with the demand”.  

“More broadly as an essential services provider we are well prepared to deal with COVID-19. Snowy Hydro is operating at full capacity and Snowy 2.0 is continuing as planned.

“Our retail business is committed to continuing to provide customers with clear and regular communication during this incredibly challenging time,” Mr Broad said.

News

Statement on some of the incorrect claims made about Snowy 2.0

16/10/2019

Snowy 2.0 is a project that is an investment for the next 100 years, that will keep Australia’s lights on, keep power prices down, and ensure Australia can make a secure transition to a clean energy future.

We note that the National Parks Association report is not an independent analysis, but just a set of random and unfounded assertions which ignore the true facts about this project.

Since construction began 70 years ago – which will be celebrated this Saturday – Snowy has provided the modern foundations of Australia’s economy, and the Snowy 2.0 project will be a bedrock for economic confidence in the future.

During that time we have been responsible environmental operators in Kosciuszko National Park and will continue to do so.

The facts are that only 0.01% of the national park will be permanently impacted by this project – or less than 1 square kilometre – of the park.

As our business and employees work and live in this area, we are committed to rehabilitating the areas affected by the Snowy 2.0 construction.

We also reject any claims that there have been cost over-runs on this project, or wild figures being promoted about the total cost of Snowy 2.0.

Our projected capital costs remain within the 2017 Feasibility Study cost of $3.8 billion to $4.5 billion and this was affirmed at the Final Investment Decision in December 2018 by Snowy Hydro’s Board, independent advisor Macquarie Capital, two government departments, Finance and Energy, and their independent advisor Lazard.

It is a falsehood to suggest transmission costs are an added cost to the Snowy 2.0 project as these are shared services used by the power industry, with the new upgraded capacity being essential in managing summer peak demand and transporting wind and solar to market.

We strongly reject any argument that Snowy 2.0 is not in the national interest. It has demonstrable economic and consumer benefits that have been independently valued at $4.4 to $6.8 billion.

News

Snowy Hydro welcomes Finkel Review

09/06/2017

Snowy Hydro Limited welcomes the support of the Finkel Review of pumped hydro as a key to energy security as it focuses on recommendations aimed at strengthening reliability in the National Electricity Market.

Snowy Hydro CEO Paul Broad said the Snowy 2.0 project would play a key role in both ensuring security of supply and backing up the expected big increase in intermittent supplies – wind and power – in the market.

The report states on p33 that “Battery and pumped hydro storage will be able to support a reliable and secure NEM, as and when they are deployed at scale.”

Mr Broad said the Finkel Review had identified the need to guarantee back-up to any new intermittent power supply projects.

“Snowy 2.0 fulfils the objectives of the Finkel Review on energy security, in that it can uniquely provide the largest scale and affordable storage of renewable energy to support the reliable and secure power supply that is needed for Australia to move safely to a low emissions economy”, Mr Broad said.

“The Finkel review rightly points to the importance of pumped hydro as an essential back-up to intermittent wind and power to protect consumers and business, and ensure we don’t face the catastrophic supply failures that we have seen in South Australia.”

Snowy Hydro also supports market-based mechanisms to achieve the Government’s commitment to climate change targets, as well as stable and long term policy certainty. We will be actively engaging with relevant bodies to implement policies which best meet the energy trilemma of market efficiency, energy security and emission reductions.

Snowy Hydro Media Enquiries:

Simon Troeth

0439 300 335

e: Simon.Troeth@newgatecomms.com.au

www.snowyhydro.com.au